Structural work on Vox Technology Park’s ground floor is in full swing. Work has been done on the ground floor and is now progressing to the first floor.
The workers are building the reinforcement framework, ready for the concrete to be poured in later.
They are working on the access ramp in the basement, with the intention of completing it by the end of this month. This will be completed in conjunction with infrastructure work.