Find out the latest news on Vox Technology Park
Want to know what we have been up to lately? Here you will find the most recent information on our building, press releases, and news.
Find out the latest news on Vox Technology Park
Urmărește progresul lucrărilor efectuate la cel mai nou hub de afaceri din Timișoara, precum și ultimele noutăți sau apariții din presă.
SkeletonCAD and Mindfully win Vox Your Startup Campaign
After several meetings with semifinalist team members and carefully analyzing each project, the jury chose to award two startups, instead of one. The Vox Your Startup campaign through which we offer a free office for two years to a startup has come to a...
Work status – November 2017
The construction of our building is approaching completion and we are preparing for the inauguration event! We are only a few weeks apart from the completion of the building, after which we can move on to the interior finishing and division of the office...
Work status – October 2017
Less than 2 months before the inauguration, the Vox Technology Park building has already become a landmark for northern Timisoara. The steel structure of the building was completed in the past month, and works on the masonry are also 100% completed. Notable progress...
What does biometric access in Vox Technology Park building actually mean?
Welcome to the business hub of the future! Acces in Vox Technology Park building will be granted through biometric authentication, using your own device. We chose this access method as it brings convenience and the highest security level for both employers...
Work status – august 2017
In August, the masonry and steel structure of the building was complete, while the facilities advanced to the upper floors. The power supply to the building is complete by 16% for high-voltage installations and 3% for low-voltage installations. HVAC and sanitary...