April was a productive month on the Vox Technology Park site, where important progress has been made to the new office building.
The work has reached the tenth floor in building A and the seventh in B2 building. B1 building is progressing well with work being carried out on the stairwells and plumbings, as the main structure is already complete.
The team has also worked on the fixtures on the first, second and third floors this month, with excellent progress made on those in the basement, which are over 80% complete.
Additionally, the windows have been mounted on the second and third floors, leaving our specialists to focus on brickwork and woodwork on the fourth floor.
We’ll keep you up to date with all the latest developments on the new business hub!