Work continues as the closed profiles for the facade woodwork are mounted. Architectural work (space partitioning) has also commenced.
In building A, the work progresses to the 7th floor, construction advances to the 6th floor in building B1 and to the 5th floor in building B2. Facility workers, finishers and facade specialists will soon begin working throughout the building.
The good weather is helping the project to evolve at a steady pace and should allow Vox Technology Park to be delivered on schedule, at the end of the year.