The new year began with lots of work at Vox building. The project is advancing on schedule, with mounting plates being installed in building A above level 5.
In the main part of the B1 building, workers are putting the vertical posts in place between the 4th and 5th floors. In the B2 building, work continues as the plate over the 3rd floor is installed.