We focused on waterproofing the exterior basement walls, pouring reinforced concrete in the vertical elements of the basement and preparing the floor.
Vox site is in full swing and takes advantage of the good weather. During this period it was achieved the basement waterproofing (outer sidewalls) and the land in the building’s proximity was also restored.
The next step was pouring reinforced concrete in the basement vertical elements (columns, diaphragm, walls) and were followed by the preparation of the floor.
We keep you updated with each construction stage of the future office building on Calea Torontalului!